Education Building Project
History And Summary of Building Needs
The campus of the First Reformed Church of New Brunswick is located in downtown New Brunswick. The campus consists of a sanctuary building, the Education Building, and the Sexton’s House (renamed in 2020 to the Barbara Littman House). All three buildings are set on a half city block.
Project’s Vision
With the permission of First Reformed Church, the vision of Town Clock Community Development Corporation is to renovate this historic Education Building, following the organization’s mission of creating permanent, affordable and safe housing with supportive services for survivors of domestic violence and their children.
Town Clock CDC envisions that this Education Building can become a true community center with the following changes:
The first floor would become a community center. Fellowship Hall would be used for workshops and community activities for the survivors of domestic violence. The kitchen would be renovated to be a nutrition and cooking center for the residents. There would be storage space and offices for First Reformed Church as well as a one-bedroom permanent, supportive, affordable housing unit with its own entry. An elevator would provide ADA access to various floors.
The second floor would offer the greatest possibility for apartments. It is the vision that there be at least four studio apartments and two 2-bedroom apartments.
The basement floor would house the heating and air conditioning systems as well as all other utilities. An expanded food and clothing pantry for the all residents who live within Town Clock CDC’s facilities would be created in the front areas of the basement.

Layout
Basement
-
BOILER ROOM/STORAGE AREA
-
MIDDLE ROOM
-
FRONT ROOM W/ WINDOWS (3)
-
STAIRWELL W/ ELEVATOR
-
FRENCH DRAINS
-
STAIRWELL (OUTSIDE) TO ENTRY DOOR
Second Floor
-
STAIRWELL (FRONT)
-
4 STUDIO APARTMENTS
-
2 TWO-BEDROOM APARTMENTS
-
STAIRWELL W/ ELEVATOR
-
LAUNDRY
-
WINDOWS (32)
Exterior Work
-
SILLS
-
SOFFITS
-
ENTRIES
-
BRICK REPOINTING
-
ENTRY BY GARBAGE CORRAL
-
BUILDING WATERPROOFING
First Floor
-
ENTRY
-
CHURCH OFFICES
-
STORAGE (NEWLY DESIGNED)
-
ONE APARTMENT (ONE BR-tbd)
-
COMMUNITY SPACE
-
STORAGE
-
KITCHEN
-
STAIRWELL W/ ELEVATOR
-
HANDICAP TOILETS
-
WINDOWS (4+9+5+9)
The Tower
-
STAIR
-
MACHINE ROOM
-
WINDOWS (8)
Project Schedule
The schedule below has been established for informational purposes. Every effort will be made to adhere to this plan, however, Town Clock CDC reserves the right to adjust the dates as required by circumstances.
Design Phase - Completed December 2023
Phase 1 Fundraising - In Progress - Goal December 2026
Phase 2 Construction Drawings - Goal January 2027
Phase 3 Construction Start - Goal March 2027
Construction Completion - September 2028
Total Square Footage is 10,980.